Class Environmental Assessment for Portage Parkway

Portage Parkway Widening and Easterly Extension to Creditstone Road

 

In May 2015, the City of Vaughan initiated an Environmental Assessment Study for Portage Parkway Widening and Extension to Creditstone Road, a strategic network improvement in the Vaughan Transportation Master Plan – A New Path (2013).

The City of Vaughan Transportation Master Plan (TMP) – A New Path (2013), companion to the City of Vaughan Official Plan (2010), identified projects that will improve connections to local and regional infrastructure, provide access to future developments, support transit-oriented nodes and corridors, and enhance transit ridership, cycling and walking.

Study Purpose

The TMP identified the need to widen Portage Parkway to four lanes from Applewood Crescent to Jane Street, and establish a new four lane road from Jane Street to Creditstone Road as a key element of the planned street network in support of the Vaughan Metropolitan Centre.

The Study is progressing to completion in accordance with "Schedule C" of the Municipal Engineers Association Municipal Class Environmental Assessment for the following projects:

 

  • Portage Parkway Widening and Easterly Extension to West of Black Creek (Part A) - COMPLETE
  • Portage Parkway Extension from West of Black Creek to Creditstone Road (Part B) - COMPLETE
     

Study Process and Timeline - COMPLETE

Consultation

A key component of the study included consultation with interested stakeholders (public and agencies). Two Public Information Centres (PICs) were held to present the study, review the study scope and discuss issues related to the project including alternative solutions, alternative designs, evaluation criteria, and environmental impacts and mitigation measures.

 

Study Chronology

Notice of Study Commencement - issued on June 12, 2015

Notice of Public Information Centre 1 - issued on November 10, 2015
- Click here to view the display boards

Notice of Public Information Centre 2 - issued on February 23, 2016

- Click here for Display Boards

- Click here for Preliminary Preferred Design

Report to Committee of the Whole - June 21, 2016

Notice of Completion - Portage Parkway Widening and Easterly Extension to West of Black Creek (Part A) - July 15, 2016 - August 15, 2016
- Environmental Study Report

Notice of Completion - Portage Parkway Widening From West of Black Creek to Creditstone Road (Part B) - September 8, 2016 - October 11, 2016


- Environmental Study Report

 

Preliminary Preferred Design and Technical Appendices

Preliminary Preferred Design - Plan and Profile

 

Environmental Study Report – Part B

Appendix A1 – Traffic Report

Appendix A2 – Safety Report

Appendix A3 – Natural Heritage Assessment

Appendix A4 – Fluvial Geomorphic

Appendix A5 – Phase One Environmental Site Assessment

Appendix A6 – Air Quality Report

Appendix A7 – Heritage Impact Assessment

Appendix A8 – Stage 1 Archaeology Assessment

Appendix A9 – Stormwater Management Report

Appendix A10 – Conceptual Storm Sewer Summary

Appendix A11 – Conceptual Stormwater Report

Appendix A12 – Tree Inventory and Assessment

Appendix A13 – Noise Impact Assessment

Appendix B – Public Consultation

 

Marta Roias, RPP

City Project Manager

City of Vaughan

2141 Major Mackenzie Dr. West

Vaughan, ON L6A 1T1

Telephone: (905) 832-2281, ext. 8026

Email: marta.roias@vaughan.ca