Kleinburg Village Improvements
Kleinburg Village Improvements continue!
We’re working to improve Kleinburg Village – and construction will resume this spring to bring roadway and streetscaping enhancements, new cycle paths (outside the village core) and more to the area.
The City of Vaughan hosted a fourth Open House on Thursday, April 16, 2026 at the McMichael Canadian Art Collection. Click here to see the presentation.
Weekly Construction Update
June 15 to 19
- Installation of boulevard pavers on Islington Avenue from Kellam Street to Stegman's Mill Road.
- Construction of road curbs and bike path on Islington Avenue from HWY 27 to Nashville Road.
- Electrical conduits & streetlight poles installation along Islington Avenue.
Temporary Parking During Construction
Alternate temporary parking will be made available just north of 10565 Islington Avenue and south of Treelawn Boulevard, and at the Kleinburg Public School (10391 Islington Ave.) from 4 p.m. to 11 p.m. on weekdays and from 6 a.m. to 11 p.m. on weekends when the work begins.
North of 10565 Islington Avenue and south of Treelawn Boulevard
Kleinburg Public School (10391 Islington Ave.)
Want to receive updates on the Kleinburg Village Improvements project? Subscribe to the project mailing list to receive construction and timeline updates.
Frequently Asked Questions