Kleinburg Village Improvements Project Updates

Construction for the Kleinburg Village Improvements Project has begun and is expected to be completed by summer 2026. 

Weekly construction updates

November 4 - 8

  • Restoration works on Nashville Road. 
  • Commissioning of watermain on Nashville Road and Islington Avenue including lane disruptions. 
  • Installation of watermain and hydrants on Islington Avenue.
  • Pole relocations on Stegman’s Mill Road by Alectra and others.
  • Night work and lane closure on Islington Avenue between Nashville Road and Stegman's Mill Road.

 

October 28 - November 1

  • Restoration works on Nashville Road. 
  • Commissioning of watermain on Nashville Road and lane disruptions. 
  • Installation of watermain and hydrants on Islington Avenue.
  • Pole relocations on Stegman’s Mill Road by Alectra and others.
  • Night work and lane closure on Islington Avenue between Nashville Road and Stegman's Mill Road.

 

October 21 - 25

  • Restoration works on Nashville Road. 
  • Commissioning of temporary watermain on Islington Avenue.  
  • Commissioning of watermain on Nashville Road and lane disruptions. 
  • Installation of watermain and hydrants on Islington Avenue.
  • Pole relocations on Stegman’s Mill Road by Alectra and others.
  • Night work and lane closure on Islington Avenue between Nashville Road and Stegman's Mill Road.

 

October 15 - 18

  • Restoration works on Nashville Road. 
  • Commissioning of temporary watermain on Islington Avenue.  
  • Commissioning of watermain on Nashville Road. 
  • Installation of watermain and hydrants on Islington Avenue.
  • Pole relocations on Stegman’s Mill Road by Alectra and others.
  • Lane closure on Islington Avenue and the Nashville Road intersection.

 

October 7 - 11

  • Restoration works on Nashville Road. 
  • Commissioning of temporary watermain on Islington Avenue.  
  • Installation of watermain on Islington Avenue.
  • Pole relocations on Stegman’s Mill Road by Alectra.
  • Lane closure on Islington Avenue and the Nashville Road intersection.

 

September 30 - October 4

  • Restoration works on Nashville Road. 
  • Commissioning of temporary watermain on Islington Avenue.  
  • Installation of watermain on Islington Avenue.
  • Grading for temporary parking lot on Islington Avenue. 

 

September 23 - 27

  • Construction of the sidewalk along Nashville Road is underway.
  • Temporary removal of electrical lighting on Nashville Road is underway. 
  • Connection and testing of the temporary watermain bypass along Nashville Road and Islington Avenue is underway.
  • Watermain installation on Nashville Road, including road cutting, is underway.  
  • Lane closure on Nashville Road.

 

September 16 - 20

  • Construction of the sidewalk along Nashville Road is underway.
  • Temporary removal of electrical lighting on Nashville Road is underway. 
  • Connection and testing of the temporary watermain bypass along Nashville Road and Islington Avenue is underway.
  • Watermain installation on Nashville Road, including road cutting, is underway. 

 

September 9 - 13

  • Construction of the sidewalk along Nashville Road is underway.
  • Temporary removal of electrical lighting on Nashville Road is underway. 
  • Installation of the temporary watermain bypass along Nashville Road and Islington Avenue is underway.
  • Watermain installation on Nashville Road, including road cutting, is underway. 

 

September 2 - 6

  • Sidewalk along Nashville Road is being prepared.
  • Electrical light standard removal on Nashville Road. 
  • Concrete for sidewalk on Nashville Road is being poured.
  • Preparation for watermain installation on Nashville Road.
  • Road cuts on Nashville Road for watermain installation.

 

August 26 - 30

  • Sidewalk along Nashville Road is being prepared.
  • Electrical light standard removal on Nashville Road. 
  • Concrete for sidewalk on Nashville Road will be poured.
  • Preparation for watermain installation on Nashville Road. (weather pending)

 

August 19 - 23

  • A temporary parking facility on Islington Avenue, north of 10565 Islington Ave. and south of Treelawn Boulevard, is being constructed. 
  • Clearing and grubbing, and tree pruning and removal along Nashville Road continues. 
  • Sidewalk along Nashville Road is being prepared.
  • Electrical conduits on Nashville Road are being installed.
  • Preparation for watermain installation on Nashville Road.
  • Soil sampling within project area will be completed. 
  • Temporary lane disruptions on Nashville Road due to soil sampling operations.

 

August 12 - 16

  • A temporary parking facility on Islington Avenue, north of 10565 Islington Ave. and south of Treelawn Boulevard, is being constructed. 
  • Clearing and grubbing, and tree pruning and removal along Nashville Road continues. 
  • Sidewalk along Nashville Road is being prepared.
  • Electrical conduits on Nashville Road are being installed.
  • Concrete for sidewalk on Nashville Road will be poured.

 

August 5 - 9

  • Construction of gravel parking lot on Islington Ave.
  • Removal of trees, clearing and grubbing on Nashville Rd.
  • Removal of sidewalk on Nashville Rd and excavation.
  • Excavation and installation of electrical conduits on Nashville Rd.

 

July 29 - August 2

  • Fencing installation.
  • Site preparation.
  • Site trailer installation.

 

July 22-26

  • Signage and fencing installation.
  • Site preparation.
  • Site trailer installation.

 

July 15-21

  • Ongoing pre-construction surveys of properties.
  • Signage and fencing installation.
  • Site preparation.

 

Community engagement

Open House #2 was held on Thursday, June 20th for residents to find out more about the scope of work, construction timelines, impacts and more. To view the presentation material please click here.

 

Open House #1 was held on Tuesday, Sept. 26 for residents to hear more about the project, receive updates on construction timelines and impacts, view renderings of what’s coming and ask questions directly to the project team. View material from the Open House (PDF).

 

Past community consultation

In 2022, residents were invited to attend a Public Information Session to learn more about the project, view a map and timelines, and ask questions directly to the project team. View the Public Information Session presentation (PDF).

 

Additional opportunities for feedback were provided throughout the following projects related to the area: