Garnet A. Williams Community Centre Renovation Project Updates

Project timeline

  • 2019: Design consultants retained, pre-design begins 
  • 2019: Preliminary design 
  • 2020: Detailed design - community engagement 
  • 2021-2022: Construction 
  • 2023: Community centre partially open!
  • 2024: Pool opens!

 

Construction Progress

July 2024

  • Pool has opened for public use
  • Pool hot tub is undergoing equipment repairs and is temporarily offline
  • Fire alarm system testing has been completed and passed inspection
  • Ongoing general construction deficiencies are being addressed
  • New Arena pad will be set up for Summer use
  • New exterior Splash pad equipment has been installed and is being commissioned. Opening Summer 2024
  • New exterior south exit stair and ramp construction is in progress
    • South exit doors leading to sun deck are RESERVED for EMERGENCY EXITING ONLY
  • Finished landscaping on the north and south sides are complete

 

Spring 2023 Construction Update

 

Construction Photos 

Pool tank

Image
Image shows GAWCC pool

 

Hot tub

Image
Image shows hot tub at GAWCC

 

Splashpad

Image
Image is of GAWCC splashpad

 

South exit stair and ramp

Image
Image shows is of the GAWCC south exit stair and ramp