Project Updates
The library and recreation activity space renovations are now complete.
- Q1 2020: Design Consultants retained, design begins (Complete)
- Q1 2021: Detailed Design (Complete)
- Q1 2021 - Q2 2021: Construction Tender (Complete)
- Q2 2021 - Q1 2022: Construction (Complete)
- Q1 2022: Renovation Complete
Join the grand re-opening celebration on Tuesday, April 26 at 9 a.m.
Citizens are invited to explore the new and improved Maple Library and Community Centre! After being closed for extensive renovations, the library branch will reopen to the public on April 26. A grand reopening celebration is being held on Tuesday, April 26, beginning at 9 a.m. The community is encouraged to come out to tour and enjoy the new spaces. The in-person event will include refreshments, on-site activities and a ribbon-cutting ceremony.
Winter 2021
- Fitness Changeroom is now open.
- Library and Recreation Activity Space finishes are being installed.
- Reopening of Maple Library planned for March
- Vaccination Centre remains operational during renovation.
Construction Progress Photos
Library Children's Area
Library Quiet Study Area
Recreation Activity Space
Fitness Changeroom
Walk through the new space:
Fall 2021
- Library and Recreation Activity Space preparing for floor, wall and ceiling finishes.
- Fitness Changeroom finishes are being installed.
- Vaccination Centre remains operational during renovation.
Summer 2021
- Library and fitness changeroom demolition nearing completion.
- Work on new walls, HVAC, electrical and structure have started.
- Vaccination Centre remains operational during renovation.
June 2021
- Gateman-Milloy Inc. has been retained as the General Contractor.
- Hoarding separating the construction area and Community Centre is complete.
- Vaccination Centre will remain operational during renovation.
- Construction has started.