A Development Application Form is required to amend the Official Plan in accordance with the Development Application Submission Process. Information related to OPA Applications can be obtained by calling 905-832-2281 or by emailing DevelopmentPlanning@vaughan.ca.
Pre-Application Consultation
Before submitting a Development Application to amend the Official Plan, the landowner may request a Pre-Application Consultation (PAC) meeting with the Development Planning Department. The purpose of this meeting is for the landowner to present a proposal and for City staff to identify, on a preliminary basis only, the required information for a complete submission of the OPA Application. Proceeding with a PAC request is at the sole discretion of the applicant. If an applicant chooses not to submit a PAC request, the City will not provide a detailed Development Application submission material checklist, and the applicant will be directed to the Vaughan Official Plan and/or PAC Complete Application Guide.
To arrange a PAC Meeting, please contact the Development Planning Department at 905-832-2281 or by emailing DevelopmentPlanning@vaughan.ca.
Submitting an OPA Application
When an OPA Application is submitted, the landowner must pay a processing fee in accordance with the in-effect Fees and Charges By-law.
The planner assigned to the file will send an acknowledgment letter to the landowner advising the file number and setting out any additional requirements to be completed. In addition, the City is required to send a "Notice of Complete Application" within 30 days of receipt of the application, if all application requirements identified at the PAC meeting, if applicable, are satisfied. If all requirements are not satisfied, a "Notice of Incomplete Application" will be sent to the landowner and processing of the application will not commence until the application requirements are fully satisfied. The application will be circulated to all internal departments and external agencies as affected.
For Official Plan Amendments and Zoning By-law Amendments, a public notification sign must be erected on the property advising of a complete application and a public meeting, and removed within 7 days of Vaughan Council or the Ontario Land Tribunal making a final decision on the application, or if there is a major change to the proposal requiring a new application and notice sign, in accordance with the City's Notice Signs Procedures and Protocols.
An OPA Application is required to be processed in accordance with the statutory timelines prescribed in the Planning Act. The process period commences once a complete application is received. If the OPA is approved, an additional surcharge fee will be required in accordance with the in-effect Fees and Charges By-law for Development Applications.
Public Meeting
Upon receipt of a complete OPA Application, a Public Meeting will be scheduled. A notice of the Public Meeting will be circulated by the City to residents within 150 metres of the area of the application at a minimum of 20 days in advance of the Public Meeting. The landowner or Agent acting on behalf of the landowner must attend this meeting to make a brief presentation of the proposal before Vaughan Council and to respond to any questions from Vaughan Council or the public.
Committee of the Whole
After the Public Meeting, the Development Planning Department is required to assess the OPA application and to receive comments and conditions from circulated parties, followed by the preparation of a Technical Report with a recommendation to the Committee of the Whole. The recommendation of the Committee of the Whole is then forwarded to the following Vaughan Council meeting for approval.
Official Plan Amendment (OPA) Approval
If the OPA application is approved, a by-law implementing the OPA is prepared by the Development Planning Department and forwarded to Vaughan Council for enactment. If the amendment has provincial interest, the amendment is forwarded to the Ministry of Municipal Affairs and Housing for approval. If the OPA application is refused, the landowner may appeal Vaughan Council's decision to the Ontario Land Tribunal (OLT) within 20 days of the Notice of Decision being issued by the Office of the City Clerk.
Ontario Land Tribunal Appeal Process
After enactment of the OPA by-law by Council, a Notice of Adoption is issued by the Office of the City Clerk to the landowner, their agent, and anyone who requested notice, as well as required agencies. This initiates a 20-day appeal period, within which anyone can appeal the Official Plan Amendment to the Ontario Land Tribunal. Once this period expires, if no appeals have been received, the in-effect by-law with the affidavit is issued to the Applicant and the OPA is deemed to have come into effect on the day Council enacted the implementing OPA by-law.